A planned shutdown gives maintenance teams a defined window to replace grate bars. Procurement is easier when the parts list, technical approvals and delivery milestones are agreed before that window begins. This guide helps boiler operators, wood panel plants and maintenance contractors organise a drawing-based spare parts order.
Start with the current equipment parts list and previous inspection records. Record the part number, drawing revision, grate position and required material for each item. Separate different lengths, handed variants and mounting arrangements instead of grouping every component under “grate bars”. Check existing stock against this list and identify parts whose revision or condition still needs review.
For a biomass boiler grate bar order, state the boiler model and fuel, such as wood chips, bark or wood processing residues. Keep service information with the purchasing specification so the supplier can review the actual application.
List the quantity intended for the shutdown separately from any reserve quantity. The plant maintenance team should establish replacement needs from inspection findings and the equipment requirements. Reserve stock should reflect the site's wear history, critical parts, existing inventory and replenishment time; one fixed percentage will not suit every grate.
If the final replacement scope will only be known after opening the furnace, record the assumptions behind the initial order. Ask the supplier to distinguish confirmed quantities from optional follow-up quantities in the quotation.
Use the required arrival date at the plant, not just the shutdown date. Confirm separate milestones for drawing approval, tooling where needed, sample approval if specified, production, inspection, packing and transport. A factory dispatch date is different from delivery to the maintenance store. Allow time for the agreed shipping route and receiving checks.
Set the approval and inspection requirements before production. Our guide to grate bar materials and inspection requirements explains which records to discuss. Any schedule depends on the final drawing, alloy, quantity and agreed inspection scope.
Request packing labels that connect each item to its part number, drawing revision and quantity. Agree which dimensional reports, material records and packing lists will accompany the shipment. Plan receiving checks early enough to raise discrepancies before the shutdown, and keep approved stock traceable by part and batch.
Send Tongzhou the itemised parts list, drawings, quantity per part, delivery destination and required arrival date. Use our replacement grate bar RFQ checklist, then contact Tongzhou to review the manufacturing scope and proposed delivery schedule.